Category Archives: Uncategorized

The changeover in the water supply starts August 2nd this will be done in two phases it will take 7- 10 days to complete: 1 st phase Nettleton area West of Hwy 371 and the Carolina Community area. Then the 2 nd phase Cason/Bigbee area and Peaceful Valley area. As we change the water over some customers may experience low pressure and dingy water. Hopefully, we can do an area in 3 days and then move to next area. Please be extremely careful washing clothes during this changeover.

Tomorrow, Wednesday June 30th, at approximately 9am, a Flow Meter is being installed on the water line at the Lee Co tank on Road 1277. The work could take approximately 4 hours the water will only be turned off as needed. After the Flow Meter is placed, we will flush the lines. This may cause low pressure and dingy water. Please be careful washing clothes. This (may or may not affect) your area depending on how much water is already in the line.